Lethbridge Construction Projects 2019

Blog

This blog  is where Onsite Safety Management strives to offer up to date information on all aspects of workplace safety. 

Lethbridge Construction Projects 2019

Onsite Safety Management Inc.

[source image]

An Economic Hub For Alberta

In 2017, Lethbridge was one of the fastest growing economies in Alberta. There was a boom in industry and growth that we continue to see today. The loyalty and pride of  Lethbridge residents is staggering. We truly value the community we live in.

Construction and skilled trades flourish in Lethbridge. Not only does this industry support permanent Lethbridge residents but it acts as a hub for the surrounding areas and many oil and gas, forestry and mining operations in Southern and Northern Alberta.

There is a long list of projects in the works within the city which will continue to support workers and create new jobs for skilled trades along with other industries.

Current Projects Happening in Lethbridge

Here’s a list of projects and plans for the city of Lethbridge in 2019:

**This list is not a complete list but it represents some of the major job creators happening now


Cycle Corridor

ACTIVE

Description

The focus of this study is to plan on-street, commuter cycling routes through Lethbridge connecting to key pathways and existing roadways as outlined in the City's Cycling Master Plan. This project will look at both on-street dedicated cycling lanes and shared cycling lanes.

Funding

City of Lethbridge - $431 000


Lethbridge Regional Park 'n' Ride Transit Terminal

ACTIVE

Description
The Lethbridge Regional Park 'n' Ride Transit Terminal will address current convenience and safety challenges in the downtown core and create an opportunity for the addition of a regional transit service.

Funding
City of Lethbridge - $4,876,000
Federal Public Transit Infrastructure Fund (PTIF) - $2,027,000
Provincial Public Transit Infrastructure Fund (PTIF) - $2,027,000
Provincial GreenTRIP - $8,080,000

Total
$17,010,000


3 Avenue South Reconstruction

ACTIVE
Description

The City of Lethbridge is excited to be embarking on a redesign and reconstruction project for 3 Avenue South. Planned changes will upgrade underground infrastructure and improve access, traffic efficiency and safety making it a more vibrant and pedestrian friendly street.

Funding
City of Lethbridge - $2,630,000
Federal Gas Tax Fund - $2,000,000
MSI Grant - $5,453,000

Total
$10,083,000


Sewer Lining

Active
Description

This project is part of the planned sewer maintenance program. Inspections in 2014 identified corrosion in the 70+ year-old-pipes. Analysis identified a need to rehabilitate the sewer lines and that relining is a lower-impact and lower-cost alternative to digging and replacing them.

Funding
Utilities Capital - $0.6 million


Legacy Park (North Regional Park)

ACTIVE

Description

The City of Lethbridge is ready to begin Phase 2 of construction at Legacy Park. Below are updates regarding different aspects included in Phase 2 development. While the park remains open to the public during construction,  patrons are asked to be aware of construction activities and comply with posted warnings and fenced off areas.

Funding
City of Lethbridge - $3,510,000
Reserve - Community Reserve - $1,000,000
Subdivision Surplus - $5,400,000
Grant - Municipal Sustainability Initiative - $12,750,000


Fire Station #5 - West Lethbridge (D-28)


Active

Description

Construction of a new Fire Station (#5) in the south end of west Lethbridge in the community of Watermark.  The new facility will be approximately 1200 sq m in size and will include three drive through apparatus bays and sufficient space for parking and fire grounds training.

Funding

Subdivision Surplus - $2.3M

Grant - Municipal Sustainability (MSI) - $9.27M

PAYG - Community - $1.03M


Wastewater Treatment Plant Biosolids Treatment Upgrades

Active
Description

The two existing Wastewater Treatment Plant digesters were constructed in 1987. A third digester was previously believed to be required to allow periodic maintenance. Implementation of new technology will allow more efficient use of the existing digester capacity and eliminate the need for a third digester.

This project will implement additional biosolids dewatering equipment and upgrade existing biosolids digester process control.
Funding
Borrowing-Utilities - $2,000,000


Whoop-Up Drive Interchange Improvements Functional Planning Study and Concept Design

COMPLETED
Description

With traffic growth on the Whoop-Up Drive, it is expected that major capacity issues will arise on the two interchanges at the east and west ends of the river crossing. With City Council wanting to delay a third river crossing as long as practical, Whoop-Up Drive remains the primary route within our transportation system connecting east and west Lethbridge.


ATB Centre - Phase 2 (D-6)


Active

Description
ATB Centre - Phase 2 will be the future home of the Cor Van Raay YMCA. This project consists of the detailed design and construction of the remaining leisure components which will adjoin to ATB Centre - Phase 1, located in the Crossings neighbourhood of west Lethbridge. At approximately 256,000 square feet, Phase 2 will include an aquatics centre with waterslides, lazy river and whirlpools, multi-sport field house, fitness centre, indoor track, gymnasiums, child minding area, indoor playground, locker rooms, commercial lease spaces, facility support and amenities.



Vacant School Site Development (D-36)


Active

Description

This project is the development of an undeveloped school site (10.7 acre), situated in the Uplands and BlackWolf neighbourhoods, that has been vacant for several years. It is located in residential areas that are almost at building completion. Many residents in this area have expressed frustration with the vacant land adjacent to their homes which is largely unusable and unattractive.

Funding
City of Lethbridge - Subdivision Surplus
$1,600,000